Skip to main content

Purified Water Generation Plant

Purified Water Generation


    Purified Water is very important part of Pharma industry used for manufacturing of tablets.There are three stages of Purified Water Generation Plant.
   Raw water from IDC received at company Raw water storage tank.From tank water transferred to PWG plant through centrifugal pumps while transferring water pass through sand filter.
Sand filter removes impurities,dust,durt partical from water.In PWG plant water pass through 5micron water filter and stored at storage tank.
   In first stage of PWG water from storage tank pass through softener plant.In softener plant hardness of water reduced also magnesium available in water removed.After softener plant NaCl and NaOH solution added in water.NaCL for jurms killing and NaOH to reduce pH of water.Then it pass through the Ultra filter in ultra filter colliden silica removed.The filter size of ultra filter is 0.1 micron to 0.01 micron.After ultra filter water stored in primary water storage tank.
   In second stage of PWG water comes from primary water storage tank through pumps.Then anti-scalent and SMBS(Sodium Meta-bisulphate) solution added in water.SMBS to remove chlorine available in water and anti-scalent for remove scale.
Then water pass through RO(Reverse osmosis) membrane with high pressure.
RO membrane filter size is 0.01 micron to 0.0001 micron.Water from RO membrane goes in EDI (Electro-Deionization) plant.In EDI plant iron present in water are removed. Water  received from EDI plant stored in Purified Water storage tank.
Conductivity of water after EDI plant should not more than 1.3 micron-siemans/meter-square.If the conductivity of water after EDI plant is less than 1.3 micron-siemans/meter-square then only water is purely Purified and it is ready for the use.If the conductivity of water is more than 1.3 micron-siemans/meter-square then the water recirculated.
    In third stage of PWG plant Purified Water stored in tank and transferred to the user department as per requirement.

Comments

Popular posts from this blog

How to control Temperature and Humidity in Air Handling Unit

  How to control Temperature and Humidity in Air Handling Unit Overview Air Handling unit is a system used to supply temperature and Humidity controlled filtered air to the cleanroom. For air filtration various types of filters are used in AHU. And for temperature and Humidity controlling cooling and heating coils are provided in AHU. Goals Control the temperature of air used in the cleanroom  Control the humidity of air used in cleanroom  Air filters Specifications    The air Handling unit consists of Air filter  Cooling coil Heating coil Air blower HEPA Filter  Controlling of Temperature and Humidity  By Cooling Method  The cooling coil recirculates the chilled water having temperatures between 4°C to 6°C. This chilled water comes from the Chiller through centrifugal pumps. When we start the Air Handling unit blowers sucks the air through the pre filters of the air Handling unit. When blowers sucks air, it passes through the cooling co...

Why ice forms at cooling coil and Suction line in Refrigeration system

 Why ice forms at cooling coil and Suction line in Refrigeration system       it's all about the relationship between a temperature and pressure and how the pressure affect the boiling point of the refrigerant. As the pressure of refrigerant increases then the temperature and boiling point also increases,  when pressure decreased temperature and boiling point also decreases. Refrigeration and air conditioning systems take use of it to cool the air or liquid.   Normal Refrigeration System      In normal refrigeration system compressor compresses the refrigerant which causes the increase in pressure and temperature of refrigerant. The hot vapour refrigerant pass through the condenser in condenser heat exchange happens and refrigerant condensate into liquid forms.Before entering in the evaporator high pressure liquid refrigerant pass through the expansion of valve. The actual device used depends on the Refrigeration system but capillary t...

HVAC Validation In pharma Industries

HVAC VALIDATION As per ISO guidelines for HVAC validation. In HVAC Validation  below points are determined and validated that they are in within range as per designed which will pass the respective ISO standard class acceptance criteria. 1)Air velocity and CFM calculation 2)Air changes per hour 3) Installed filter leakage test 4) HEPA filter integrity test 5)Air flow pattern test or smoke test 6)Partical count test 7)Total variable count 8) Temperatur and pressure monitoring 9) Temperature and Humidity recovery test 10) Fresh air calculation All this points are determined recorded in documents.All this validation process done by validation contractors under observation of respective company Engineer. 1) Air velocity and CFM calculation :-   - Scan the area of the HEPA filter with probe of anemometer 6 inches from the filter face. - For accurate velocity take the velocity of air at five place of filters ( Four corners and centre of filter) - Record the air velocity i...